Electrical¶
100A → 200A service upgrade. Standard LED-dimmable switches. Outlets replaced. EV conduit stub-out. Cat6 drops. Lighting plan TBD per room.
Locked¶
- Service upgrade: 100A → 200A (required for heat pump + induction + future EV)
- Outlets: replace every receptacle house-wide; GFCI/AFCI per code, tamper-resistant, weather-resistant in wet zones
- Switches: LED-compatible dimmable standard switches (Lutron Diva or equivalent); skip smart-switch ecosystem
- EV charger: conduit + 50A breaker stub-out now; charger deferred (see budget for full / skip alts)
- Ethernet: 2–3 hardwired Cat6 drops to ceilings (main central, upper central, possibly modem area)
- Existing baseboard circuits removed (replaced by heat pump)
Open / to price¶
- Confirm 100A is current service (check main breaker label)
- Sub-panel needed (upper floor / kitchen) or single panel sufficient?
- Panel location — keep or relocate?
- Number of Cat6 drops — 2 / 3 / more
- Lighting plan per room — recessed cans, pendants, sconces, task; switching layout (worth a session per room)
- Kitchen outlet strategy — backsplash vs. pop-up; USB-C in island
- Exterior lighting — entry, deck, condenser pad, pathway
- Hot water heater electrical (if HPWH alt)
- Hot tub disconnect — being removed (see Rec room)
- Sauna heater electrical — typ. 6–9 kW = 30–40A 240V; coord. Sauna
Cost overview options¶
EV charger (radio)
| Option | Cost | Notes |
|---|---|---|
| Conduit + 50A breaker stub-out (chosen) | $300–800 | Cheapest insurance |
| Full Level 2 charger installed | $1.5–3k | All-in upfront |
| Retrofit after walls closed | $2.5–4k+ | What we're avoiding |
| Skip | $0 | Foregone |
Cat6 drops (radio)
| Option | Cost |
|---|---|
| 3 drops (main + upper + modem) | $300–600 |
| 2 drops (main + upper) | $200–400 |
| Skip | $0 |
See main budget to toggle.
Refs¶
- HVAC — heat pump load
- Kitchen — induction range circuit (40A, 240V)
- Plumbing — gas tankless impacts venting/electric only minimally
- Decisions log
Load math for 200A
| Load | Approx. amps |
|---|---|
| High-velocity heat pump | ~30A |
| Induction range | ~40A |
| Heated floor (main bath) | ~5A |
| Future EV charger | ~50A |
| Hot water (if HPWH alt) | ~30–60A |
| Lighting + outlets + balance | balance |
100A trips on concurrent load. 200A leaves headroom for EV. 400A would only matter with EV + spa + workshop stacking.